From client — change to requirements, Milan

Ingested 1 hr ago by nora.chen@meridian-labs.com. The text submitted to this workspace, kept exactly as it arrived.
Typeproject-noteAuthority0.50Referenceclearpath-email-external-010Locator04-external-comms/email/email-external-010.mdEvent date3 Nov 2025Ingested23 Oct 2026Records supported1Length1039 charactersContent hashsha256:17f5e8bf120c…PermalinkNot recorded
# Email: Change to requirements — additional area **From:** Priya Anand (ClearPath Solutions) **To:** Marcus Webb **Date:** November 3, 2025, 14:20 **Subject:** Change to requirements — additional area --- Hi Marcus, I have a scope question that came up in conversation with Thomas. He feels strongly that the review should include an assessment of our Milan satellite office operations. I understand this is a late addition and falls outside the original SOW, but he wants to ensure we have a complete operational picture. The Milan office is small (8 people, mostly administrative roles) and handles light compliance work, but Thomas sees it as part of the overall operational footprint we should understand. I know we're well into the analysis phase, but wanted to flag this directly rather than have it come as a surprise. What would it take to incorporate Milan into the engagement? Thanks for your flexibility. Priya Anand Head of Operations ClearPath Solutions Inc. priya.anand@clearpath-solutions.it

What was taken from it

Show all
“He feels strongly that the review should include an assessment of our Milan satellite office operations.”✓ Verified · Characters 298–402, found at the stored offsetsAssertedThe CEO asks for Milan to be assessed, a late addition outside the original Statement of Work.